2023 CFSEI DESIGN EXCELLENCE AWARD WINNERS
NON-BUILDING APPLICATION – FIRST PLACE
SALAS O'BRIEN – SOUTHWEST DOWNTOWN PEDESTRIAN BRIDGE COLORADO SPRINGS, COLORADO
Southwest Downtown Pedestrian Bridge W. Vermijo Avenue & S. Sierra Madre Street Colorado Springs, CO 80903
Completion Date: July 2021 Completion Date: $20 million
Owner: City of Colorado Springs, Colorado Architect of Record: Andrew G. Nielsen, Diller Scofidio+Renfro LLC Engineer of Record for Structural Work: Jerry L. Brock, Arup North America, LTD Cold-Formed Steel Specialty Engineer: Russ Leffler, Salas O’Brien Cold-Formed Steel Specialty Contractor: Kyle Montague, Spacecon Award Entry Submitted by: Ryan Nelson, Salas O’Brien
Project Background
The “bridge of the future” is a 250-foot-long, 550-ton pedestrian bridge that connects the U.S. Olympic and Paralympic Museum with America the Beautiful Park. The bridge was fabricated in Houston, Texas in six separate sections and transported to Colorado Springs, Colorado to be constructed. This unique bridge is a hybrid steel structure combing an arch and a truss into two interlocking, twisting loops to form an oculus in the middle span that opens up to gorgeous views of Pikes Peak and downtown Colorado Springs.
Design Challenges and Solutions
We were tasked with designing the 5400 cold-formed metal framing supporting the canted wall panels that wrapped the inside of the twisting oculus. The cold-formed steel (CFS) framing gradually curved and varied in height on each end, above and below the oculus. The biggest challenge presented by the CFS design was dealing with the three-dimensional and rotational movement of the steel structure as it induced thermal, wind, seismic, and live loads. To accommodate the complex movements in the bridge superstructure, each stud was rigidly fastened to the varying upper steel structure while the base was fastened to the concrete bridge with SL clips. The base connection only used two screws to the SL clips so that the connection could handle the rotational demands along with the vertical movement in the bridge.
It took several iterations and meetings with the engineer of record, panel manufacturer and contractor to secure the final design. Each element required an allowable tolerance of movement so that the panels could achieve their flawless smooth appearance. The completed project is impressive and appreciated by visitors.
|